North Yorkshire Field Borrowed for a Six-Year-Late Power Link
BAM wants a 2.06-hectare Drax yard for Eastern Green Link 2, the 2GW cable now due in 2029 rather than 2023.
BAM has asked North Yorkshire Council for a 2.06-hectare storage yard beside Drax, the last local piece of a £4.3bn Scotland-England power link due in 2029. The extra compound would sit on farm land east of Wren Hall Lane, about 400 metres from the power station, where the converter hall for the 2GW cable is already rising.
Construction of the yard is pencilled in for December 2026, if the council agrees. The field would then hold kit through 2027 and 2028 for Eastern Green Link 2, the joint-venture cable from Peterhead that was once wanted in service by 2023.
BAM Wants 2.06 Hectares East of Wren Hall Lane
The application, filed by BAM, covers agricultural land east of Wren Hall Lane and would feed the existing EGL2 compound across a temporary haul-road crossing. Mott MacDonald, which wrote the planning statement, said the extra space is needed so the main works can proceed “efficiently and safely” and so lorries make fewer wasted trips on surrounding land.
The statement backs the yard “in principle due to its essential role in facilitating the delivery of the EGL2 Project, which constitutes a nationally significant infrastructure scheme.” BAM says the compound would not add traffic beyond movements already approved for the converter and cable works.
WHAT THE EXTRA COMPOUND WOULD HOLD
- Soil stores: Separate areas for topsoil and subsoil stripped from the field.
- Security kit: A kiosk, temporary lighting, CCTV towers and fencing around the plot.
- Haul-road crossing: A temporary crossing of Wren Hall Lane linking the new yard to the compound already in use.
- Working hours: 7am to 7pm on weekdays and 8am to 5pm on Saturdays, with Sunday work only in exceptional cases.
Those hours are tighter on Sundays than the converter site next door, which already has permission for Sunday shifts. The yard itself would be built between December 2026 and March 2027, used from April 2027 until September 2028, then taken down so the field can go back to farming between October and December 2028.
What EGL2 Will Carry Between Peterhead and Drax
Eastern Green Link 2 is a joint venture of National Grid Electricity Transmission and SSEN Transmission. It is a 525kV high-voltage direct-current link, built to move power both ways between Aberdeenshire and Yorkshire, and the joint venture presents it as a 505km between Peterhead and Drax route with 436km of cable under the North Sea and 68km buried across the East Riding from Fraisthorpe Sands.
Prysmian is supplying about 1,000km of cable for the bipole. Hitachi Energy and BAM are delivering the converter stations at each end. Balfour Beatty is installing the English onshore stretch. Ofgem gave final approval on project costs on 13 August 2024, and the first earth was turned at both ends the following month. The stated aim is enough clean power for up to two million homes, in service in 2029.
THE DRAX END OF EGL2
| Piece | Scale | Status |
|---|---|---|
| Wren Hall converter | Four-metre-high platform, buildings going up | Construction since September 2024 |
| East Riding underground cable | 68km from the coast to Drax | Enabling and trench works through 2026 |
| Proposed extra compound | 2.06 hectares, 400 metres from the power station | Decision pending; build window December 2026 to March 2027 |
Cable laying is due in 2027 and 2028, which is why BAM now wants more laydown space just as the onshore route moves from surveys into open-cut trenches and drills under roads and rivers.
The 2015 Plan Called for Power by 2023
The extra field is a small planning ask. The wait behind it is not. Ten years ago the system operator’s Network Options Assessment said a Peterhead project of this kind should proceed with an expected delivery date of 2023. Outline planning for the Drax converter came in August 2023. Final cost approval followed in August 2024. Energisation is now put at 2029, six years later than that 2023 date.
FROM A 2023 TARGET TO A 2029 SWITCH-ON
- 2015: The Network Options Assessment calls for a Peterhead link with an expected delivery date of 2023.
- August 2023: North Yorkshire Council grants outline permission for the Wren Hall converter station.
- 13 August 2024: Ofgem issues its EGL2 project assessment decision.
- September 2024: Groundbreaking is held at Peterhead and at Wren Hall on the same day.
- October 2026: BAM submits the extra 2.06-hectare compound application.
- December 2026 to March 2027: Proposed construction window for the new yard.
- April 2027 to September 2028: Yard in use for 18 months.
- October to December 2028: Land restored to farming.
- 2029: EGL2 is due to start carrying power.
The UK Energy Research Centre, looking at 2024 constraint data, said a 2GW uplift delivered on that original 2023 timetable could have avoided 73 percent of thermal constraint costs. A 1GW uplift, in the same analysis, would have tackled 45 percent. Those figures are a model of a missed 2023 date, not a forecast of 2029. They still measure the gap this Yorkshire yard is now being asked to serve.
Constraint Bills Have Already Beaten the 2025 Total
While steel goes up at Wren Hall, the grid is still paying Scottish wind farms to stop and paying gas plants closer to demand to start. Octopus Energy’s Wasted Wind tracker, drawing on Elexon data, said on 5 October 2026 that Britain had already past last year’s entire £1.47 billion bill, with three months of 2026 still to run. The 2026 running total at that point was £1.51bn, some £40 million above the whole of 2025.
September 2026 was the costliest month in the tracker’s record at £404.3 million, and 30 September alone cost £30 million. NESO has forecast £3.2 billion in constraint costs in the year to July 2027. A government warning puts the figure as high as £10 billion by 2030 if the wires stay tight. Some Scottish transmission boundaries, including B4, have been running at about 40 percent of capacity while upgrade outages take circuits out.
We’ve already blown past last year’s entire bill, and customers are paying every pound of that waste. It’s madness.
Greg Jackson, founder and chief executive, Octopus Energy, 5 October 2026 note
The Drax landing is the east-coast link already in the ground. Later cables toward Lincolnshire and Norfolk are still in consenting, so they will not cut the 2026 bill. EGL2 is built to run south and north, which matters when English plant is long and Scottish wind is short, but the expensive hours are still the ones when Scottish turbines are told to feather and gas sets light up.
Why a Flood-Zone Field Is Being Borrowed
The 2.06 hectares sit in Flood Zone 3. The application includes flood measures, and BAM Nuttall has already sought an environmental permit for dewatering at the Wren Hall converter, discharging up to 5 cubic metres a day of trade effluent to an Internal Drainage Board drain. Wildlife surveys have flagged possible effects on bats, badgers and breeding birds, with more survey work and mitigation proposed.
WHAT WE KNOW
- The ask: 2.06 hectares of farm land, a haul-road crossing, and an 18-month operating window from April 2027.
- The flood setting: The plot is in Flood Zone 3, and dewatering at the converter has already gone through an Environment Agency advert.
- The traffic claim: BAM says the yard would not create trips beyond those already approved for EGL2.
WHAT IS UNCONFIRMED
- The decision: North Yorkshire Council has not yet determined the application.
- The wildlife package: Further surveys are proposed; the final mitigation is not settled in public papers attached to this filing.
- The flood detail: Measures are described, not tested in a published decision notice.
The planning statement leans on the yard’s temporary life. Once the converter and the 68km cable no longer need the extra ground, the soil goes back and the field is supposed to farm again. That is the bargain being put to the council: borrow a flood-plain paddock for two winters so a 2GW cable can be finished.
Steel Is Already Up at the Wren Hall Site
The compound application reads like a new project. It is overflow from one that is 25 months old. Construction started in September 2024 at Wren Hall and at Peterhead together. At Drax, site set-up, a four-metre platform, piling, works on the existing 400kV substation and a 132kV overhead-line diversion are already in train. Trial trenching has been done at 261 points on the southern cable route. On 19 October 2026 the project closed Main Road in Drax for bellmouth works.
Project pages list Sunday working at Wren Hall until March 2027 from 8am to 5pm, on top of the weekday 7am to 7pm pattern used along the English route. Peterhead has been on planned 24-hour working from 5 October to 30 November 2026. The extra Drax yard is how a site that has already eaten its first compound keeps materials off the lane.
A year on, we can already see the scale of that ambition taking shape, with foundations now in place at both converter station sites and teams across Scotland and England working tirelessly to make progress on this colossal project.
Fionán Doonan, EGL2 project director, joint-venture one-year construction note
Deputy project director Neil Lyons called the first year “laying strong foundations, both literally and figuratively.” Cable laying in 2027 and 2028 is the next physical join between the two converter halls. The Wren Hall yard BAM now wants is the English store cupboard for that join.
The Compound Would Come Down by December 2028
If North Yorkshire Council grants the application, the extra yard would be built through the winter of 2026 and 2027, run for 18 months, and be cleared by December 2028. EGL2 is due to start carrying 2GW a year after that. Until then the same billpayers who will fund the cable are still paying to switch Scottish wind off and to fire gas in its place.
-
AUTO2 months agoVolkswagen Sells the Osnabruck Plant to Clear a Board Fight
-
NEWS3 months agoApple’s Foldable iPhone Hinges on Samsung Display Supply
-
BUSINESS3 months agoSaksham Gaur Finds He Is His Own Company’s Client
-
AUTO3 months agoTata Motors’ Iveco Tender Opens as Holders Still Decide
-
TECHNOLOGY3 years agoWhat Is SD on Amazon Prime?
-
BUSINESS3 months agoHyderabad 22-Carat Gold Jumps After a False Bargain
-
GAMING3 months agoOnimusha Way of the Sword Preload Hits a Windows 11 Wall
-
BUSINESS3 months agoUltraTech Ultravolt Launch Splits Friday Stocks to Watch