Loch Indaal Leaves Cemre More Than 20 Months Late
CMAL took Loch Indaal more than 20 months late from a prepaid Turkish yard, and Islay still waits for the first sailing.
Caledonian Maritime Assets Limited accepted delivery of MV Loch Indaal at Cemre Marin Endustri in Yalova, Turkey, on 18 November 2026, more than 20 months after the planned handover. The diesel-electric ferry is 94.8 metres long and is built for 450 passengers and 100 cars, or 14 commercial vehicles. She still has to cross from the Sea of Marmara, then complete crew drills in Scotland, before CalMac can put her on the Islay run.
Ministers called the ceremony a step toward better island services. The dates around that ceremony are less kind. CMAL had said she would be handed over in February 2025. The public body already paid the last contract cash in June, and CalMac has still not named a first sailing.
CMAL Takes Loch Indaal After More Than 20 Months
The Maritime and Coastguard Agency and Lloyd’s Register have certified the ship. CalMac will sail her to Scotland, then run crew familiarisation and local trials before she joins sister ship MV Isle of Islay on the Kennacraig to Islay service. Cabinet Secretary for Transport Stephen Flynn said the vessel would leave Cemre soon and enter service at the earliest opportunity for island communities and businesses.
Full focus is now on preparing the vessel for CalMac’s transfer to Scotland and subsequent operational readiness activities allowing for entry into service at the earliest opportunity for the benefit of our island communities and businesses. The vessel will depart Cemre soon.
Stephen Flynn, Cabinet Secretary for Transport, CMAL handover statement
CMAL chief executive Kevin Hobbs said the yard had worked under difficult global circumstances and that Loch Indaal would be a welcome addition when she joins Isle of Islay. CalMac chief executive Duncan Mackison said the sister ship had already proved useful on Islay and on other routes when required. None of those statements includes a date on which a car can book Kennacraig to Port Askaig on the new hull.
THE FOUR CEMRE FERRIES
| Ship | Intended routes | Where the programme stands |
|---|---|---|
| MV Isle of Islay | Islay and Jura | In service since 31 March 2026 |
| MV Loch Indaal | Islay and Jura | Handed over 18 November 2026, voyage pending |
| MV Lochmor | Skye Triangle / Little Minch | Delivery due in the first quarter of 2027 |
| MV Claymore | Skye Triangle / Little Minch | Launched 2 May 2026, delivery due in the second quarter of 2027 |
CMAL ordered the pair for Islay to lift vehicle and freight capacity on those routes by a combined 40% and to ease pressure on an ageing major-vessel fleet. The two later hulls are meant for the Little Minch, linking Skye with Harris and North Uist. Until Loch Indaal finishes her trials, the Islay timetable still runs without her.
The February 2025 Delivery Date Did Not Hold
CMAL awarded Cemre a £91 million contract in March 2022 for the two Islay ships after a competitive tender. First steel was cut on 3 October 2022. The first hull was due in October 2024, with the second to follow in early 2025. When Loch Indaal left the slipway on 8 June 2024, CMAL put a public date on that second handover: February 2025.
🎉 Exciting News 🎉
Today we're announcing that MV Loch Indaal will be launched on 8 June 2024, at Cemre Shipyard in Yalova, Turkey. She'll be the sister ship of MV Isle of Islay and is set to be delivered in February 2025.
Read the full story at: https://t.co/oaDCxaTybK pic.twitter.com/MmFr5DWVSQ
— CMAL (@CMAssets) May 3, 2024
That date moved in pieces. Shipyard labour, kit from original equipment makers, Red Sea disruption, the war in Ukraine, and the 2023 Turkey-Syria earthquakes were all cited at different times. In September 2026 CMAL told Holyrood’s transport committee the ship would come in October, about 20 months late. At the end of October, Hobbs wrote again: specialist engineers were missing, MCA inspectors would return in the week beginning 9 November, and handover would slip to mid-November, with seven to ten days then needed to prepare the crossing.
FROM STEEL CUT TO HANDOVER
- March 2022: CMAL awards Cemre the £91 million Islay pair, with the first ship due in October 2024 and the second in early 2025.
- 8 June 2024: Loch Indaal is launched at Yalova, and CMAL states a February 2025 delivery.
- 15 January 2026: Isle of Islay is handed over, about 15 months after her original October 2024 date.
- 31 March 2026: Isle of Islay enters service on Kennacraig to Port Askaig.
- 11 to 18 June 2026: Loch Indaal completes acceptance sea trials on the Sea of Marmara.
- 25 June 2026: CMAL pays the remaining contract balance and takes legal ownership of the three unfinished hulls.
- 18 November 2026: Loch Indaal is formally handed over, more than 20 months after February 2025.
The explanations never settled on one cause, which is how a February 2025 ship became a November 2026 ship. Missing OEM engineers in October sat outside the yard’s control, in CMAL’s telling, as had earlier shocks in the supply chain. Two years of those outside events is now the delivery record.
Why Scotland Paid for Unfinished Ships in June
By late June the remaining three Cemre hulls were still unfinished, and the yard was under money pressure. On 25 June 2026 CMAL paid the leftover milestone cash, a remaining balance of £23 million, and took legal title to Loch Indaal, Lochmor, and Claymore. Hobbs called it a precaution, meant to protect money already spent if Cemre’s position got worse. In a worst case the hulls could be towed elsewhere to be finished, at further public cost.
While we are disappointed by the circumstances that have led to this decision, our priority remains the completion of these vessels for the communities that depend on them. Taking ownership of the vessels at this stage is a precautionary move to reduce risk, protect the investment already made and support our objective of bringing these vessels into service as quickly and efficiently as possible.
Kevin Hobbs, Chief Executive, CMAL, 26 June 2026 statement
Hobbs’s letter to the transport committee the same week said Loch Indaal was around 97 percent complete at purchase, with passenger lounges, RoRo kit, paint, and final MCA and Lloyd’s inspections still to close. Lochmor was around 90 percent complete. Claymore, launched on 2 May 2026, was around 85 percent complete. The ships were already UK-registered. The yard kept building them.
PUBLIC MONEY ON THE CEMRE SHIPS
- First Islay pair: £91 million, awarded in March 2022 for Isle of Islay and Loch Indaal.
- Four-ship programme: two contracts in 2022 and 2023 totalling about £200 million (US$263 million).
- June 2026 title move: £23 million remaining balance paid on 25 June so CMAL owned the three unfinished hulls.
- Extra project costs: ministers approved around £20 million in September 2026 for CMAL’s added project spend, a separate pot from the £23 million contract balance.
Flynn said CMAL would keep ownership and manage costs for the rest of the build, with staff on site and senior visits. The design and build contract for two Islay ferries had been sold as a way to get hulls without waiting on the Clyde. The June cheque was the bill for keeping that bet alive. Cemre still had to finish the ships. Scotland already owned them.
Isle of Islay Needed Dry Dock After 15 Weeks
Isle of Islay is the only working proof of this design in CalMac colours, and her first months cut both ways. She was handed over on 15 January 2026, left Turkey later that month, and berthed at Inchgreen dock in Greenock at 10am on 22 February after a 4400 nautical mile sail to Greenock. The crew met winter storms in the western Mediterranean, three named storms in Hobbs’s later account, and stopped off Morocco to pick up a person in the water. Planned as a run of about two weeks, the winter crossing filled the weeks from late January to 22 February.
She entered service on 31 March 2026 on Kennacraig to Port Askaig. Mackison now calls her a valuable member of the fleet. Six weeks after those first passengers, a hinge fault on the bow doors forced her to load only from the stern. CalMac kept the timetable going. On 15 July she went into Dales dry dock in Greenock, 15 weeks after entering service, for about two weeks of work on the bow ramp and a forward bow thruster, plus around 150 lesser warranty jobs. CalMac called that a normal first-in-class list. MV Isle of Arran, built in 1983, covered the route with MV Finlaggan.
The same ship is already being used as a spare. CalMac’s service desk said Isle of Islay would run Ullapool to Stornoway from 15 to 27 November 2026 because MV Loch Seaforth’s overhaul had slipped. That is the cascade Flynn talks about, and it is happening while Loch Indaal is still in Yalova. Islay’s new hull is on the Minch. The second new hull has not started home.
The Winter Crossing Comes Before Any Islay Sailing
Handover is not a sailing, and the sister ship’s winter run is the closest guide. A CalMac spokesperson said crews will spend about seven to ten days with Loch Indaal in Turkey before departure, then a 2.5-week voyage to Greenock, subject to weather and sea conditions. Familiarisation in Scotland should be shorter than the six weeks Isle of Islay needed, because the class is no longer new to the company. CalMac will set an entry date only after she arrives, and it will be after the festive period, around February.
No entry-into-service date has been posted, so the live CalMac timetable is still the one islanders book against. A November departure into the same waters that held Isle of Islay for weeks is not a two-week certainty. Storms, bunkering calls, and crew hours can stretch the diary before any berthing trial at Kennacraig or Port Askaig even starts.
STILL TO COME BEFORE ISLAY SERVICE
- Yard time: about seven to ten days with the CalMac crew in Turkey before she sails.
- The crossing: a planned 2.5-week run to Greenock, open to weather, on the same Marmara-to-Clyde track that took Isle of Islay from late January to 22 February.
- Scottish trials: crew familiarisation and local berthing checks, shorter than the six weeks spent on the first ship.
- First passengers: after the festive period, around February, on a date CalMac has not confirmed.
The harbours are not the hold-up. CMAL’s enabling works at Kennacraig, Port Askaig, and Colonsay, including dredging, fendering, stronger berths, and shore power, were finished in time for the new class and later won Project of the Year and the Marine Award at the Scottish Civil Engineering Awards on 25 September 2026. The terminals were ready while Loch Indaal was still waiting for OEM engineers in Yalova.
Lochmor and Claymore Are Still Scheduled for 2027
Two more ships remain at Cemre. Lochmor’s sea trials were planned for November 2026, with delivery in the first quarter of 2027. Claymore, launched on 2 May 2026, is due in the second quarter of 2027. Both are assigned to the Skye Triangle. Those dates have already moved once, and they sit on the same yard that needed a prepaid balance to keep work going.
Scottish ministers announced new Islay ships as far back as April 2018, to replace MV Hebridean Isles and to work with MV Finlaggan. The 2022 order was meant to close that wait. Ferguson Marine, the nationalised Clyde yard then stuck on its own late builds, did not win the tender. Cemre did. Four years after first steel, half the four-ship order is in Scottish hands, one hull is in service, and the second is certified beside a Turkish quay.
Flynn said Loch Indaal and Isle of Islay will improve reliability and efficiency on Islay and help the wider network through cascade. That cascade is already visible on Stornoway, which is a better argument for the class than the handover speeches. It is also a reminder that one working new ship is being stretched across a thin fleet while her sister is still a delivery voyage away.
Loch Indaal is now a Scottish-owned, MCA-certified ferry. She is still in the Sea of Marmara. Islay gets her after the winter crossing, the trials, and a date CalMac has not set.
-
AUTO3 months agoVolkswagen Sells the Osnabruck Plant to Clear a Board Fight
-
NEWS3 months agoApple’s Foldable iPhone Hinges on Samsung Display Supply
-
BUSINESS3 months agoSaksham Gaur Finds He Is His Own Company’s Client
-
AUTO3 months agoTata Motors’ Iveco Tender Opens as Holders Still Decide
-
TECHNOLOGY3 years agoWhat Is SD on Amazon Prime?
-
BUSINESS3 months agoHyderabad 22-Carat Gold Jumps After a False Bargain
-
GAMING3 months agoOnimusha Way of the Sword Preload Hits a Windows 11 Wall
-
ENTERTAINMENT2 years agoAndy Scott’s Steel Loon Repeats the Kelpies Regeneration Bet